Free Pike Bridge Schedule Update

Charles WheelerCommunity News

The milling and paving schedule for the Free Pike Bridge is scheduled to begin on Friday, June 9, and will end on Friday, June 16, weather permitting.


Project Schedule: 

Road Closed:                                                                                                May 5, 2022

Design-Build Document Preparation:         May 5, 2022 – October 10, 2022

Right-of-Way Acquisition:                              November 2022 – January 2023

Advertise & Award:                                                           March 2023 – April 2023

Design & Construction:                                     June 2023 – September 29, 2023*

* The road is required by contract to be open by September 29, 2023. Some minor construction activity, such as planting grass, may occur after the road is open. Final contract completion date is scheduled for October 27, 2023. 